Project
duroZINQ finishing of steel structures with a total weight of approximately 5,000 tonnes, which were to be used in the course of modernization work for the Burglengenfeld cement plant. In detail, in addition to a new heat exchanger tower, two new raw mills, a modern fabric filter for exhaust gas dedusting, a bypass filter, and a new clinker cooler were planned for the plant.
Realisation
Various subcontractors were entrusted with the manufacture of the necessary steel components, the majority of which sent their steel to ZINQ for surface finishing, more precisely to the plants in Gelsenkirchen, Landsberg and Bydgoszcz in Poland. The components were delivered to Burglengenfeld phase by phase by the ZINQ plants and in part by the subcontractors.